Below is a recap of the meeting from MON. NOV. 25 that occurred at the Celina Police Department Headquarters.
- The Board unanimously approved the hire of a new Special Projects Consultant to work with the board and our general manager on several major projects in 2025 – pumps, wells, irrigation, erosion, traffic signs, speed/school zones, landscaping, dredging, etc.
- Other Key Updates:
- Engineer advised that the City of Celina has authorized a traffic study for a stoplight at Bridgewater/Frontier – updates will be provided as available
- Warrant studies for stop-signs at Cypress Creek/LF Way and Forefront/Light Creek Ln and a crosswalk at Sweetwater/Light Farms Way will be completed in mid-January
- Board unanimously approved the following work to be done:
- Walking trail improvements behind Sweetwater/Grange
- Erosion repairs on Maydelle Ave
- Moving our irrigation well pump reading to our GM, saving the district over $10,000 per year
- The board awaits bids for other erosion and landscaping issues across the neighborhood
The next meeting will be on MON. JAN. 6 at 6:00 PM in the community room at the Celina Police Headquarters (3025 S Coit Rd)